(SeeNews) - Mar 12, 2014 - The delayed launch of two power substations of Brazilian utility Chesf forced local electricity sector regulator Aneel to order postponement of the start of nine wind power plants of overall 177.8 MW capacity of local renewable energy developer Renova Energia (BVMF:RNEW3) for January 2015.