Construction complete for 402-MW Veja Mate offshore wind park

Source: Veja Mate Offshore Project GmbH (www.vejamate.net)

May 31 (Renewables Now) - The 402-MW Veja Mate offshore wind farm in the German North Sea has completed construction, the project company, Veja Mate Offshore Project GmbH, said today.

The last of the wind farm's 67 Siemens SWT-6.0-154 turbines was installed last Thursday and commissioning activities were completed today.

All 67 turbines are now feeding electricity into the German grid, almost four months ahead of schedule agreed at financial close, said chief executive Henrik Scheinemann.

The EUR-1.9-billion (USD 2.1bn) wind farm is owned by Highland Group Holdings Ltd, Siemens Financial Services and a fund managed by Copenhagen Infrastructure Partners (CIP). Its construction was completed in less than 14 months and 23 months after financial close.

Veja Mate is expected to produce more than 1.6 TWh of electricity per year.

(EUR 1 = USD 1.117)

More stories to explore
Share this story
Tags
About the author
Browse all articles from Plamena Tisheva

Plamena has been a UK-focused reporter for many years. As part of the Renewables Now team she is taking a keen interest in policy moves.

More articles by the author
5 / 5 free articles left this month
Get 5 more for free Sign up for Basic subscription
Get full access Sign up for Premium subscription