All turbines installed at 353-MW Galloper wind farm

Source: Twitter, @innogy_uk

December 22 (Renewables Now) - All 56 turbines have been installed at the 353-MW Galloper offshore wind farm off the coast of Suffolk in the UK, German energy firm Innogy SE (ETR:IGY) said today.

The wind farm features Siemens Gamesa turbines of 6.3 MW, the first of which was installed in May this year. First power was generated in early November.  

The focus now will be on completing the commissioning works, with the project expected to be finished in the spring of 2018, the German company said.   

Innogy is in charge of the wind farm's construction and operation on behalf of the project partners, which also include Macquarie Capital, Sumitomo Corp (TYO:8053) and Siemens Financial Services.

"At 180 metres tall, these are the biggest offshore wind turbines we’ve installed to date plus we’ve installed them in water up to 36 metres deep, so quite a feat of engineering and construction," said project director Toby Edmonds.

More stories to explore
Share this story
Tags
About the author
Browse all articles from Plamena Tisheva

Plamena has been a UK-focused reporter for many years. As part of the Renewables Now team she is taking a keen interest in policy moves.

More articles by the author
5 / 5 free articles left this month
Get 5 more for free Sign up for Basic subscription
Get full access Sign up for Premium subscription